Lender guide · Clace Research
Underwriting GPU-backed loans
Underwrite the cash the borrower can collect and the money a lender could recover by selling the equipment. Lenders and insurers should test both when customer contracts end before the debt matures, site power arrives late, or GPU resale values fall. This guide walks through the evidence to ask for and a worked downside case.
What if the GPU customer contract expires before the loan?
Measure the principal still outstanding on the expiry date after scheduled amortization and any enforceable cash sweep. Compare that balance with cash from replacement contracts, allowing for idle months, lower GPU rental rates and the cost of bringing a new customer on. If the stressed cash flow leaves a payment gap, quantify how much must be repaid before expiry or supported by reserves or a guarantee.
Start with the borrowing entity, its enforceable customer contracts and the assets it can pledge. Map the cash waterfall to each debt tranche. Ask what keeps paying if the customer disputes acceptance, terminates or runs out of funding. Model debt service coverage using cash available after operating costs and required reserves.
What would we recover if we had to sell the GPUs?
Estimate net sale proceeds for the whole fleet at the size and speed a lender could execute. Verify title, serial numbers, physical location, liens and rights to enter the site and remove the equipment. Deduct removal, testing, storage and selling costs, and any prior claims on the proceeds. In The Hardware Lottery, Levered, Clace Research founder Joshua Kattapuram explains how block size can affect GPU clearing prices.
When can a data center start billing if grid power is delayed?
Use the earliest date the customer contract allows the borrower to invoice. If billing depends on customer acceptance, tie it to the utility and commissioning milestones that make the contracted load available. Model what a three- or six-month slip does to interest and reserves. Reconcile megawatts requested, capacity committed by the utility, capacity delivered to the site and the load that can run after commissioning. Ask for the executed utility agreement, milestones by phase, equipment lead times and the acceptance tests that release customer billing.
What evidence supports the next construction draw?
Tie the draw to evidence such as an independent engineer's report, equipment delivery, commissioning or customer acceptance. Compare the schedule with work in place and confirm that the remaining budget, including contingency, covers completion. Identify who funds overruns and what happens to interest and principal if a milestone slips. Track building completion, power delivery and customer acceptance as separate dates.
Which permits or rules could affect repayment or recovery?
Identify the permits and rules that affect construction, operation and collateral recovery. Ask counsel to confirm permit status, power and operating restrictions, and applicable export or end-use controls for the expected buyers and destinations. Test the effect of a smaller resale market or a slower permit on the cash and recovery cases.
How should a life insurer stress long-dated AI infrastructure debt?
Start with the legal borrower and trace each payment to the tenant, operator, guarantor or pledged asset that supports it. Model payment timing and the amount at risk at each major contract expiry. In one scenario, delay power delivery and customer acceptance together. In another, assume a tenant fails to renew, GPU rental and resale prices fall together, and refinancing is more expensive or delayed.
Run the same shocks across the portfolio. Two loans can depend on the same tenant, guarantor, utility or GPU generation even when the borrowers are different. For each scenario, record how much principal is exposed, how long cash receipts are delayed and how much the portfolio could recover before treating the exposures as diversified. CREFC Data Center Primer · PIMCO's credit market analysis
Worked example
An illustrative facility has $60 million outstanding when its anchor customer contract expires. Stressed cash available for annual debt service is $12 million against $15 million of scheduled payments, or 0.80× debt service coverage. A sale of the fleet yields $54 million before $6 million of removal and sale costs and $3 million of prior claims. Net collateral proceeds are $45 million, or 75% of principal before timing and any other recoveries. Cash that depends on operating the fleet and proceeds from selling the same fleet belong in separate scenarios.
The two gaps tell the credit committee where to focus. Faster amortization before expiry can reduce the balance at risk. A funded reserve can cover a temporary payment gap. Evidence of replacement contracts or executable block-sale bids makes the downside easier to price. The numbers are hypothetical and do not represent an observed transaction or a target lending threshold.
How does CoreWeave DDTL 5.5 handle shorter customer contracts?
CoreWeave disclosed a $2.6 billion delayed-draw term loan, DDTL 5.5, in August 2026. The borrower is CoreWeave Financing DDTL V-V, LLC. CoreWeave reported an approximately five-year facility maturity and average underlying customer contract lengths of approximately three years. The borrower must apply excess cash flow to monthly prepayments after the commitment period until the outstanding principal reaches $1.3 billion. To quantify the exposure past contract expiry, model the balance remaining after scheduled paydowns and the sweep under both timely and delayed renewals. CoreWeave Form 8-K · Issuer announcement · Credit agreement, sections 2.08–2.09 · CoreWeave Form 10-Q
Prepared by Clace Research for institutional lenders and insurers. This guide does not provide investment advice.